QUESTION:

Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activities she will need to do and their estimated times.

a. Arrange the activities into two logical sequences.

b. (1) Construct an AOA network diagram.

(2) Construct an AON diagram.

c. Determine the critical path and the expected duration time.

d. What are some possible reasons for the project to take longer than the expected duration?

Estimated Time (hrs.) ___________________ Activity (abbreviation)

0.8 ———————————————– Install the software (Inst)

0.4 ————————————————- Outline the paper (Out)

0.2 —————————— Submit the paper to the instructor (Sub)

0.6 —————————————————— Choose a topic (Ch)

0.5 ——— Use grammar-checking routine and make corrections (Ck)

3.0 ——- Write the paper using the word- processing software (Write)

2.0 ——————————————- Shop for a new computer (Sh)

1.0 ———————————– Select and purchase a computer (Sel)

2.0 ————————– Do library research on the chosen topic (Lib)


You must be registered and logged in to an account to download the solution

Reviews

There are no reviews yet.

Be the first to review “Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer.”

Your email address will not be published.