Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks.

$1.49 Excluding Tax

Complete Solution:

Solution Available in PDF File.

-
+

Description

QUESTION:

Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.


 