The development of a new deluxe version of a particular software product is being considered by Ravi Behara’s software house. The activities necessary for the completion of this project are listed in the following table:

(a) What is the project completion date?

(b) What is the total cost required for completing this project at a normal time?

(c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?

(d) What is the maximum time that can be crashed? How much would costs increase?


You must be registered and logged in to an account to download solution


Reviews

There are no reviews yet.

Be the first to review “Development of a new deluxe version of a particular software product is being considered by Ravi Behara’s”

Your email address will not be published.