For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and

$1.49 Excluding Tax

Complete Solution:

Solution Available in PDF File.

-
+

Description

QUESTION:

For each of the problems listed, determine the following quantities for each activity: the earliest start time, latest start time, earliest finish time, latest finish time, and slack time. List the critical activities, and determine the expected duration of the project.

a. Problem 1 a.

b. Problem 1 b.