Using Johnson’s for 2 machine scheduling, the sequence is:
Scheduled Order __________________ Job
1 …………………………………………. C
2 …………………………………………. B
3 …………………………………………. E
4 …………………………………………. A
5 …………………………………………. D
6 …………………………………………. F
For the schedule developed using Johnson’s rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter response as a whole number).
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting Processing times are as follows:
Job…….Operation 1…….Operation 2
…………(hours)………..(hours)
A………….12……………..4
B…………..8…………….11
C…………..5…………….14
D…………..6……………..2
E…………..9…………….10
F…………..3……………..1